Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 19, 2023 | Assent Application Received |
Jan 24, 2023 | Administrative Review for Completeness |
Feb 24, 2023 | Eng Team Review for Completeness |
Feb 24, 2023 | Project Manager |
Feb 24, 2023 | Application Accepted |
Feb 24, 2023 | Category B assigned |
Mar 06, 2023 | 30 day Public Notice Issued |
Mar 15, 2023 | HPHC Historical Preservation No Effect |
Apr 06, 2023 | Public Notice End Date |
Apr 28, 2023 | Engineering Report |
May 18, 2023 | Dock/1.1.6 Review approval |
Jun 07, 2023 | Typist for Processing |
Jun 07, 2023 | Executive Sign Off |
Jun 07, 2023 | Sent to Photo Copy |
Jun 07, 2023 | Permit Approved |
Jun 07, 2023 | Permit Mailed |
Jun 22, 2023 | Land Evidence Date |
Jul 17, 2023 | Commencement of Work Notice received |