Action Date | Action Description |
---|---|
Oct 26, 2004 | Application Accepted |
Nov 15, 2004 | Historical Preservation Approval Granted |
Feb 01, 2005 | US Army Corp of Engineers Permit Date |
Feb 03, 2005 | US Army Corps of Engineers Approval Received |
Feb 25, 2005 | Category B assigned |
May 27, 2005 | Supervisor Biologist SignOff |
Jun 01, 2005 | Executive Sign Off |
Jun 21, 2005 | Mail Agenda Notice |
Jun 21, 2005 | Ready to Schedule Semi-Monthly Meeting |
Jun 28, 2005 | Semi-Monthly Meeting Date Scheduled |
Jun 28, 2005 | Semi-Monthly Meeting Held |
Jun 28, 2005 | Council Approval Granted |
Jul 11, 2005 | Stipulation Package by Engineer |
Jul 11, 2005 | Typist for Processing |
Jul 11, 2005 | Executive Sign Off |
Jul 11, 2005 | Sent to Photo Copy |
Jul 11, 2005 | Permit Approved |
Aug 29, 2005 | Correspondence Mailed/Faxed/E-mailed |
Sep 06, 2005 | Assent Correction Request Received |
Sep 07, 2005 | Typist for Processing |
Sep 07, 2005 | Executive Sign Off |
Sep 07, 2005 | Sent to Photo Copy |
Sep 07, 2005 | Assent Correction Mailed |
Sep 29, 2005 | Typist for Processing |
Sep 29, 2005 | Land Evidence Date |
Jan 20, 2006 | Legal Response/Decision |