Action Date | Action Description |
---|---|
Jan 11, 2005 | Assent Application Received |
Jan 12, 2005 | Administrative Review for Completeness |
Jan 21, 2005 | Team Review for Completeness |
Jan 21, 2005 | Application Accepted |
Jan 21, 2005 | Category A* (Docks) |
Feb 01, 2005 | 30 day Public Notice Issued |
Feb 14, 2005 | HPHC Review Pending |
Feb 28, 2005 | Public Notice End Date |
Mar 10, 2005 | Correspondence Received |
Jun 16, 2005 | Plans Received |
Jun 20, 2005 | 30 day Public Notice Issued |
Jul 18, 2005 | US Army Corp of Engineers Permit Date |
Jul 20, 2005 | US Army Corps of Engineers Approval Received |
Jul 20, 2005 | Public Notice End Date |
Aug 09, 2005 | Biologist Report |
Aug 09, 2005 | Engineering Report |
Aug 11, 2005 | Supervisor Biologist SignOff |
Aug 11, 2005 | Executive Sign Off |
Sep 07, 2005 | Ready to Schedule Semi-Monthly Meeting |
Sep 08, 2005 | Mail Agenda Notice |
Sep 13, 2005 | Semi-Monthly Meeting Held |
Sep 13, 2005 | Supervisor Engineer SignOff |
Sep 13, 2005 | Semi-Monthly Meeting Date Scheduled |
Sep 19, 2005 | Biologist Report |
Sep 19, 2005 | Council Approval Granted |
Sep 21, 2005 | Executive Sign Off |
Sep 21, 2005 | Legal Response/Decision |
Sep 22, 2005 | Typist for Processing |
Sep 22, 2005 | Executive Sign Off |
Sep 22, 2005 | Sent to Photo Copy |
Sep 22, 2005 | Permit Approved |
Sep 22, 2005 | Stipulation Package from Biologist |
Sep 22, 2005 | Stipulation Package by Engineer |
Oct 17, 2005 | Land Evidence Date |
Apr 13, 2006 | Commencement of Work Notice received |