Action Date | Action Description |
---|---|
Jan 11, 2005 | Assent Application Received |
Jan 12, 2005 | Administrative Review for Completeness |
Jan 14, 2005 | Team Review for Completeness |
Jan 14, 2005 | Application Accepted |
Jan 14, 2005 | Category A* (Docks) |
Jan 20, 2005 | 30 day Public Notice Issued |
Jan 28, 2005 | HPHC Review Pending |
Jan 31, 2005 | 30 day Public Notice Issued |
Feb 21, 2005 | Dock Subcommittee Meeting Held |
Feb 23, 2005 | US Army Corp of Engineers Permit Date |
Feb 24, 2005 | US Army Corps of Engineers Approval Received |
Feb 25, 2005 | Biologist Report |
Feb 25, 2005 | Engineering Report |
Mar 01, 2005 | Executive Sign Off |
Mar 02, 2005 | Public Notice End Date |
May 03, 2005 | Ready to Schedule Semi-Monthly Meeting |
May 03, 2005 | Mail Agenda Notice |
May 10, 2005 | Semi-Monthly Meeting Held |
May 10, 2005 | Council Approval Granted |
May 10, 2005 | Semi-Monthly Meeting Date Scheduled |
May 16, 2005 | Stipulation Package from Biologist |
May 16, 2005 | Stipulation Package by Engineer |
May 18, 2005 | Typist for Processing |
May 18, 2005 | Executive Sign Off |
May 18, 2005 | Sent to Photo Copy |
May 18, 2005 | Permit Approved |
Jun 02, 2005 | Land Evidence Date |
Sep 19, 2005 | Biologist Report |
Sep 19, 2005 | Executive Sign Off |
Sep 19, 2005 | Legal Response/Decision |