Action Date | Action Description |
---|---|
Commencement of Work Notice received | |
Feb 04, 2005 | Assent Application Received |
Feb 07, 2005 | Administrative Review for Completeness |
Feb 07, 2005 | Team Review for Completeness |
Feb 07, 2005 | Application Accepted |
Feb 07, 2005 | Category A* (Docks) |
Feb 14, 2005 | 30 day Public Notice Issued |
Feb 15, 2005 | HPHC Review Pending |
Mar 16, 2005 | Public Notice End Date |
Mar 17, 2005 | Correspondence Received |
Mar 25, 2005 | Dock Subcommittee Meeting Held |
Mar 25, 2005 | Dock sub-committee Approved |
Mar 25, 2005 | Biologist Report |
Mar 25, 2005 | Engineering Report |
Mar 31, 2005 | Typist for Processing |
Mar 31, 2005 | Executive Sign Off |
Mar 31, 2005 | Sent to Photo Copy |
Mar 31, 2005 | Permit Approved |
Apr 15, 2005 | Land Evidence Date |