Action Date | Action Description |
---|---|
Feb 07, 2005 | Assent Application Received |
Feb 08, 2005 | Administrative Review for Completeness |
Apr 13, 2005 | Team Review for Completeness |
Apr 13, 2005 | Application Accepted |
Apr 22, 2005 | Historical Preservation Approval Granted |
Apr 27, 2005 | HPHC Review Pending |
Jun 03, 2005 | Biologist Report |
Jun 03, 2005 | Typist for Processing |
Jun 03, 2005 | Executive Sign Off |
Jun 03, 2005 | Sent to Photo Copy |
Jun 03, 2005 | Permit Approved |
Oct 12, 2005 | Commencement of Work Notice received |
Feb 22, 2006 | Correspondence Received |
Jul 19, 2006 | Site Inspection |
Jul 20, 2006 | Correspondence Mailed/Faxed/E-mailed |