Action Date | Action Description |
---|---|
Feb 11, 2005 | Assent Application Received |
Feb 15, 2005 | Administrative Review for Completeness |
Feb 23, 2005 | Deficient Application - Owner Notification Sent |
Mar 08, 2005 | Deficient Application Picked Up |
Mar 31, 2005 | Deficiency Response Received |
Apr 11, 2005 | Deficient Application Picked Up |
Apr 28, 2005 | Deficiency Response Received |
May 02, 2005 | Team Review for Completeness |
May 02, 2005 | Application Accepted |
May 02, 2005 | Category B assigned |
May 17, 2005 | 30 day Public Notice Issued |
Jul 15, 2005 | Correspondence Received |
Jul 15, 2005 | Correspondence Received |
Jul 20, 2005 | Public Notice End Date |
Jul 21, 2005 | HPHC Review Pending |
Jul 26, 2005 | Historical Preservation Approval Granted |
Aug 26, 2005 | Plans Received |
Sep 08, 2005 | Water Quality Certification |
Oct 04, 2005 | Biologist Report |
Oct 04, 2005 | Engineering Report |
Oct 06, 2005 | Plans Received |
Oct 07, 2005 | Plans Received |
Oct 11, 2005 | Supervisor Biologist SignOff |
Oct 11, 2005 | Supervisor Engineer SignOff |
Oct 12, 2005 | Executive Sign Off |
Oct 19, 2005 | Ready to Schedule Semi-Monthly Meeting |
Oct 19, 2005 | Mail Agenda Notice |
Oct 25, 2005 | Semi-Monthly Meeting Held |
Oct 25, 2005 | Council Approval Granted |
Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled |
Nov 29, 2005 | Legal Response/Decision |
Dec 06, 2005 | Permit Approved |
Dec 06, 2005 | Stipulation Package from Biologist |
Dec 06, 2005 | Stipulation Package by Engineer |
Dec 06, 2005 | Typist for Processing |
Dec 06, 2005 | Executive Sign Off |
Dec 14, 2005 | Sent to Photo Copy |
Dec 14, 2005 | Chairman's Signoff |