Action Date | Action Description |
---|---|
Mar 08, 2005 | Assent Application Received |
Mar 09, 2005 | Administrative Review for Completeness |
Mar 11, 2005 | Deficient Application - Owner Notification Sent |
Apr 07, 2005 | Deficiency Response Received |
Apr 15, 2005 | Team Review for Completeness |
Apr 15, 2005 | Application Accepted |
Apr 15, 2005 | HPHC Review Pending |
May 03, 2005 | Historical Preservation Approval Granted |
May 12, 2005 | Biologist Report |
May 13, 2005 | Typist for Processing |
May 13, 2005 | Executive Sign Off |
May 13, 2005 | Sent to Photo Copy |
May 13, 2005 | Permit Approved |
May 19, 2005 | Land Evidence Date |
Jul 28, 2006 | Modification Request |
Jul 31, 2006 | Administrative Review for Completeness |
Aug 07, 2006 | Team Review for Completeness |
Aug 17, 2006 | Engineering Report |
Aug 17, 2006 | Typist for Processing |
Aug 17, 2006 | Executive Sign Off |
Aug 17, 2006 | Sent to Photo Copy |
Aug 17, 2006 | Modification Approved |
Aug 22, 2006 | Land Evidence Date |