Action Date | Action Description |
---|---|
Aug 20, 2004 | Assent Application Received |
Feb 23, 2005 | Correspondence Received |
Mar 15, 2005 | Application Accepted |
Mar 15, 2005 | 30 day Public Notice Issued |
Apr 01, 2005 | Plans Received |
Apr 07, 2005 | Correspondence Received |
Apr 11, 2005 | Objections/Comments Received |
Apr 15, 2005 | Public Notice End Date |
Apr 18, 2005 | Correspondence Received |
Jun 09, 2005 | Correspondence Mailed/Faxed/E-mailed |
Jun 09, 2005 | Correspondence Mailed/Faxed/E-mailed |
Jun 13, 2005 | Correspondence Received |
Jun 14, 2005 | Correspondence Received |
Jun 15, 2005 | Prehearing Conference |
Jun 17, 2005 | Objections/Comments Received |
Jun 27, 2005 | Correspondence Received |
Jul 01, 2005 | Correspondence Received |
Jul 05, 2005 | Correspondence Received |
Jul 05, 2005 | Correspondence Received |
Jul 07, 2005 | Correspondence Mailed/Faxed/E-mailed |
Jul 07, 2005 | Correspondence Received |
Jul 15, 2005 | Public Hearing Continued |
Jul 18, 2005 | Public Hearing Scheduled |
Sep 14, 2005 | Correspondence Received |
Nov 01, 2005 | Correspondence Received |
Nov 16, 2005 | Correspondence Received |
Dec 13, 2005 | Correspondence Mailed/Faxed/E-mailed |
Nov 05, 2007 | File Closed |
Nov 05, 2007 | Public Hearing Notices Mailed |