Action Date |
Action Description |
Mar 18, 2005 |
Assent Application Received |
Mar 24, 2005 |
Administrative Review for Completeness |
Apr 05, 2005 |
Team Review for Completeness |
Apr 05, 2005 |
Application Accepted |
Apr 05, 2005 |
Category B assigned |
Apr 14, 2005 |
Correspondence Received |
Apr 18, 2005 |
HPHC Review Pending |
Jun 15, 2005 |
30 day Public Notice Issued |
Jun 16, 2005 |
Additional Information Received |
Jul 14, 2005 |
Correspondence Received |
Jul 15, 2005 |
Objections/Comments Received |
Jul 15, 2005 |
Objections/Comments Received |
Aug 05, 2005 |
Correspondence Received |
Aug 05, 2005 |
Correspondence Received |
Aug 15, 2005 |
Public Notice End Date |
Apr 21, 2006 |
Correspondence Received |
Jul 17, 2006 |
Correspondence Received |
Oct 30, 2006 |
Correspondence Mailed/Faxed/E-mailed |
Jul 11, 2007 |
Additional Information Received |
Jul 26, 2007 |
Correspondence Received |
Aug 07, 2007 |
Correspondence Received |
Aug 23, 2007 |
Correspondence Mailed/Faxed/E-mailed |
Aug 31, 2007 |
Plans Received |
Aug 31, 2007 |
Correspondence Received |
Nov 13, 2007 |
Plans Received |
Jan 02, 2008 |
Mail Agenda Notice |
Jan 10, 2008 |
Correspondence Received |
Jan 15, 2008 |
Council Approval Granted |
Jan 15, 2008 |
Semi-Monthly Meeting Date Scheduled |
Jan 22, 2008 |
Biologist Report |
Feb 20, 2008 |
Historical Preservation Approval Granted |
Feb 20, 2008 |
Water Quality Certification |
Feb 26, 2008 |
Water Quality Certification |
Mar 11, 2008 |
Legal Response/Decision |
May 23, 2008 |
Correspondence Received |
Sep 26, 2008 |
Correspondence Mailed/Faxed/E-mailed |
Dec 17, 2009 |
Additional Information Received |
Dec 23, 2009 |
Permit Approved |
Dec 23, 2009 |
Stipulation Package from Biologist |
Dec 23, 2009 |
Stipulation Package by Engineer |
Dec 30, 2009 |
Conservation Easement Mailed. |
Jan 05, 2010 |
Conservation Easement Recording received |
Jan 05, 2010 |
Land Evidence Date |
Oct 30, 2014 |
Correspondence Received |
Nov 13, 2014 |
Correspondence Received |
Dec 24, 2014 |
Plans Received |
Aug 07, 2018 |
Modification Request |
Aug 08, 2018 |
Administrative Review for Completeness |
Aug 28, 2018 |
Team Review for Completeness |
Aug 28, 2018 |
Deficient Application - Owner Notification Sent |
Oct 30, 2018 |
Deficient Application Picked Up |
Nov 07, 2018 |
Deficiency Response Received |
Nov 14, 2018 |
Team Review for Completeness |
Nov 16, 2018 |
Application Accepted |
Dec 12, 2018 |
HPHC Historical Preservation No Effect |
Apr 04, 2019 |
Plans Received |
Apr 12, 2019 |
Extension of Permit Request |
Apr 25, 2019 |
Enforcement Compliance Inspection Required |
Apr 25, 2019 |
Process Extension |
Apr 25, 2019 |
Extension Approved |
May 14, 2019 |
Additional Information Received |
May 16, 2019 |
Biologist Report |
May 16, 2019 |
Engineering Report |
May 17, 2019 |
Typist for Processing |
May 17, 2019 |
Executive Sign Off |
May 17, 2019 |
Sent to Photo Copy |
May 17, 2019 |
Modification Approved |
May 28, 2019 |
Land Evidence Date |
May 11, 2020 |
Extension of Permit Request |
May 14, 2020 |
Enforcement Compliance Inspection Required |
May 14, 2020 |
Process Extension |
May 14, 2020 |
Extension Approved |