Action Date | Action Description |
---|---|
Mar 31, 2005 | Assent Application Received |
Apr 01, 2005 | Administrative Review for Completeness |
May 05, 2005 | Deficient Application - Owner Notification Sent |
May 12, 2005 | Deficiency Response Received |
May 24, 2005 | Deficient Application - Owner Notification Sent |
May 25, 2005 | Deficiency Response Received |
Jun 02, 2005 | Team Review for Completeness |
Jun 02, 2005 | Application Accepted |
Jun 14, 2005 | Review on Hold |
Jun 14, 2005 | Correspondence Received |
Jun 16, 2005 | Plans Received |
Jun 20, 2005 | Typist for Processing |
Jun 20, 2005 | Executive Sign Off |
Jun 20, 2005 | Sent to Photo Copy |
Jun 20, 2005 | Permit Approved |
Jun 20, 2005 | Biologist Report |
Jun 22, 2005 | Land Evidence Date |
Jun 24, 2005 | Commencement of Work Notice received |