Action Date | Action Description |
---|---|
Apr 11, 2005 | Assent Application Received |
Apr 12, 2005 | Team Review for Completeness |
Apr 12, 2005 | Application Accepted |
Apr 13, 2005 | Administrative Review for Completeness |
May 03, 2005 | HPHC Review Pending |
May 04, 2005 | Biologist Report |
May 05, 2005 | Typist for Processing |
May 05, 2005 | Executive Sign Off |
May 05, 2005 | Sent to Photo Copy |
May 05, 2005 | Permit Approved |
Jun 06, 2005 | Land Evidence Date |
Mar 19, 2008 | Extension of Permit Request |
Apr 16, 2008 | Enforcement Compliance Inspection Required |
Apr 16, 2008 | Process Extension |
Apr 16, 2008 | Executive Sign Off |
Apr 16, 2008 | Extension Approved |
Jun 05, 2009 | Extension of Permit Request |
Jun 18, 2009 | Extension Cancelled |