Action Date | Action Description |
---|---|
Apr 18, 2005 | Assent Application Received |
Apr 18, 2005 | Administrative Review for Completeness |
May 10, 2005 | Team Review for Completeness |
May 10, 2005 | Application Accepted |
May 17, 2005 | 30 day Public Notice Issued |
May 20, 2005 | HPHC Review Pending |
May 27, 2005 | Dock Subcommittee Meeting Held |
May 27, 2005 | Dock sub-committee Approved |
Jun 14, 2005 | US Army Corp of Engineers Permit Date |
Jun 17, 2005 | US Army Corps of Engineers Approval Received |
Jun 17, 2005 | Public Notice End Date |
Jul 11, 2005 | Correspondence Received |
Jul 11, 2005 | Typist for Processing |
Jul 11, 2005 | Executive Sign Off |
Jul 11, 2005 | Sent to Photo Copy |
Jul 11, 2005 | Permit Approved |
Jul 11, 2005 | Engineering Report |
Aug 24, 2005 | Land Evidence Date |
Jul 15, 2022 | Modification Request |
Jul 22, 2022 | Administrative Review for Completeness |
Jul 26, 2022 | Bio Team Review for Completeness |
Jul 26, 2022 | Project Manager |
Aug 02, 2022 | HPHC Historical Preservation No Effect |
Aug 31, 2022 | 30 day Public Notice Issued |
Sep 30, 2022 | Public Notice End Date |
Oct 05, 2022 | Biologist Report |
Oct 19, 2022 | Typist for Processing |
Oct 19, 2022 | Executive Sign Off |
Oct 19, 2022 | Sent to Photo Copy |
Oct 19, 2022 | Permit Mailed |
Oct 19, 2022 | Modification Approved |
Oct 04, 2023 | Land Evidence Date |