Action Date | Action Description |
---|---|
Apr 18, 2005 | Assent Application Received |
Apr 18, 2005 | Administrative Review for Completeness |
May 05, 2005 | Deficient Application - Owner Notification Sent |
Jun 14, 2005 | Deficiency Response Received |
Jun 14, 2005 | Administrative Review for Completeness |
Jun 17, 2005 | Application Accepted |
Jun 17, 2005 | Team Review for Completeness |
Jul 08, 2005 | 30 day Public Notice Issued |
Jul 14, 2005 | Engineering Report |
Jul 29, 2005 | Dock Subcommittee Meeting Held |
Aug 08, 2005 | Public Notice End Date |
Aug 23, 2005 | Biologist Report |
Aug 24, 2005 | Typist for Processing |
Aug 24, 2005 | Executive Sign Off |
Aug 24, 2005 | Sent to Photo Copy |
Aug 24, 2005 | Permit Approved |
Sep 12, 2005 | US Army Corp of Engineers Permit Date |
Sep 15, 2005 | US Army Corps of Engineers Approval Received |
Sep 21, 2005 | Land Evidence Date |