Action Date | Action Description |
---|---|
May 23, 2005 | Assent Application Received |
May 23, 2005 | Administrative Review for Completeness |
Jun 28, 2005 | Team Review for Completeness |
Jun 28, 2005 | Application Accepted |
Jul 14, 2005 | HPHC Review Pending |
Nov 10, 2005 | Additional Information Received |
Nov 14, 2005 | 30 day Public Notice Issued |
Dec 12, 2005 | Engineering Report |
Dec 13, 2005 | Biologist Report |
Dec 13, 2005 | Supervisor Biologist SignOff |
Dec 13, 2005 | Executive Sign Off |
Dec 14, 2005 | Public Notice End Date |
Dec 29, 2005 | US Army Corp of Engineers Permit Date |
Jan 03, 2006 | US Army Corps of Engineers Approval Received |
Feb 23, 2006 | Mail Agenda Notice |
Feb 23, 2006 | Ready to Schedule Semi-Monthly Meeting |
Mar 14, 2006 | Semi-Monthly Meeting Date Scheduled |
Mar 21, 2006 | Mail Agenda Notice |
Mar 28, 2006 | Semi-Monthly Meeting Held |
Mar 28, 2006 | Council Approval Granted |
Mar 28, 2006 | Semi-Monthly Meeting Date Scheduled |
Apr 12, 2006 | Stipulation Package from Biologist |
Apr 12, 2006 | Stipulation Package by Engineer |
Apr 12, 2006 | Legal Response/Decision |
Apr 12, 2006 | Typist for Processing |
Apr 12, 2006 | Executive Sign Off |
Apr 12, 2006 | Sent to Photo Copy |
Apr 12, 2006 | Permit Approved |
Apr 18, 2006 | Land Evidence Date |