Action Date | Action Description |
---|---|
Jun 23, 2005 | Assent Application Received |
Jun 24, 2005 | Administrative Review for Completeness |
Jun 27, 2005 | Team Review for Completeness |
Jun 27, 2005 | Application Accepted |
Jul 11, 2005 | Additional Information Requested from Applicant |
Jul 14, 2005 | HPHC Review Pending |
Sep 23, 2005 | Engineering Report |
Sep 26, 2005 | Biologist Report |
Sep 26, 2005 | Plans Received |
Sep 28, 2005 | Typist for Processing |
Sep 28, 2005 | Executive Sign Off |
Sep 28, 2005 | Sent to Photo Copy |
Sep 28, 2005 | Permit Approved |
Oct 07, 2005 | Land Evidence Date |
Nov 09, 2005 | Commencement of Work Notice received |