Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Aug 21, 2012 | Assent Application Received |
Aug 22, 2012 | Administrative Review for Completeness |
Aug 28, 2012 | Team Review for Completeness |
Aug 28, 2012 | Application Accepted |
Sep 12, 2012 | HPHC Historical Preservation No Effect |
Nov 07, 2012 | Additional Information Received |
Nov 26, 2012 | 30 day Public Notice Issued |
Dec 26, 2012 | Public Notice End Date |
Jan 18, 2013 | Category B assigned |
Feb 04, 2013 | Biologist Report |
Feb 08, 2013 | US Army Corps of Engineers Approval Received |
Feb 15, 2013 | Typist for Processing |
Feb 15, 2013 | Permit Approved |
Feb 19, 2013 | Executive Sign Off |
Feb 19, 2013 | Sent to Photo Copy |
Feb 26, 2013 | Land Evidence Date |
Jul 06, 2017 | Expiration of Assent/End of Tolling Legislation |
Dec 19, 2017 | Modification Request |
Dec 20, 2017 | Administrative Review for Completeness |
Dec 20, 2017 | Team Review for Completeness |
Dec 20, 2017 | Application Accepted |
Jan 26, 2018 | HPHC Historical Preservation No Effect |
Feb 14, 2018 | Biologist Report |
Feb 14, 2018 | Modification Approved |
Feb 28, 2018 | Land Evidence Date |