Action Date | Action Description |
---|---|
Dec 22, 2015 | Freshwater Wetland - Preliminary Determination |
Dec 22, 2015 | Administrative Review for Completeness |
Dec 28, 2015 | Team Review for Completeness |
Dec 28, 2015 | Team Review for Completeness |
Dec 28, 2015 | Application Accepted |
Feb 01, 2016 | Additional Information Requested from Applicant |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Feb 23, 2016 | Plans Received |
Mar 21, 2016 | Plans Received |
Mar 25, 2016 | Biologist Report |
Mar 25, 2016 | Engineering Report |
Mar 29, 2016 | Typist for Processing |
Mar 30, 2016 | Executive Sign Off |
Mar 30, 2016 | Sent to Photo Copy |
Mar 30, 2016 | Permit Approved |
Apr 06, 2016 | Land Evidence Date |