Action Date | Action Description |
---|---|
Dec 23, 2015 | Assent Application Received |
Dec 23, 2015 | Administrative Review for Completeness |
Dec 29, 2015 | Team Review for Completeness |
Dec 29, 2015 | Application Accepted |
Dec 29, 2015 | Permit Approved |
Jan 28, 2016 | Biologist Report |
Jan 29, 2016 | Typist for Processing |
Jan 29, 2016 | Executive Sign Off |
Jan 29, 2016 | Sent to Photo Copy |
Feb 08, 2016 | HPHC Historical Preservation No Effect |
May 06, 2016 | Land Evidence Date |
Dec 12, 2016 | Modification Request |
Dec 12, 2016 | Administrative Review for Completeness |
Dec 13, 2016 | Team Review for Completeness |
Dec 13, 2016 | Plans Received |
Dec 13, 2016 | Application Accepted |
Dec 15, 2016 | Biologist Report |
Dec 19, 2016 | Typist for Processing |
Dec 19, 2016 | Executive Sign Off |
Dec 19, 2016 | Sent to Photo Copy |
Dec 19, 2016 | Modification Approved |
Dec 27, 2016 | HPHC Historical Preservation No Effect |