Action Date | Action Description |
---|---|
Dec 30, 2015 | Assent Application Received |
Dec 31, 2015 | Administrative Review for Completeness |
Dec 31, 2015 | Team Review for Completeness |
Dec 31, 2015 | Application Accepted |
Jan 04, 2016 | Plans Received |
Jan 21, 2016 | Additional Information Received |
Jan 29, 2016 | Biologist Report |
Feb 02, 2016 | Typist for Processing |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Feb 04, 2016 | Executive Sign Off |
Feb 04, 2016 | Sent to Photo Copy |
Feb 04, 2016 | Land Evidence Date |
Feb 04, 2016 | Permit Approved |