Action Date | Action Description |
---|---|
Dec 30, 2015 | Assent Application Received |
Dec 31, 2015 | Administrative Review for Completeness |
Jan 04, 2016 | Team Review for Completeness |
Jan 04, 2016 | Team Review for Completeness |
Jan 04, 2016 | Application Accepted |
Jan 06, 2016 | Biologist Report |
Jan 06, 2016 | Engineering Report |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Feb 17, 2016 | Typist for Processing |
Feb 18, 2016 | Executive Sign Off |
Feb 18, 2016 | Sent to Photo Copy |
Feb 18, 2016 | Permit Approved |
Mar 07, 2016 | Land Evidence Date |