Action Date | Action Description |
---|---|
Jan 25, 2022 | Maintenance Certification Request |
Jan 28, 2022 | Administrative Review for Completeness |
Feb 04, 2022 | Eng Team Review for Completeness |
Feb 10, 2022 | Bio Team Review for Completeness |
Feb 10, 2022 | Application Accepted |
Feb 11, 2022 | Project Manager |
Feb 16, 2022 | Biologist Report |
Feb 21, 2022 | Typist for Processing |
Feb 21, 2022 | Executive Sign Off |
Feb 21, 2022 | Sent to Photo Copy |
Feb 21, 2022 | Permit Approved |
Feb 25, 2022 | HPHC Review Pending |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 28, 2022 | Permit Mailed |
Mar 03, 2022 | Land Evidence Date |
Nov 09, 2022 | Dock Post-Construction Certification by Engineer received. |