Action Date | Action Description |
---|---|
Jan 28, 2022 | Assent Application Received |
Feb 01, 2022 | Administrative Review for Completeness |
Feb 01, 2022 | CHA Worksheet received |
Feb 07, 2022 | Bio Team Review for Completeness |
Feb 07, 2022 | Deficient Application - Owner Notification Sent |
Mar 14, 2022 | Deficiency Response Received |
Mar 24, 2022 | Bio Team Review for Completeness |
Mar 24, 2022 | Application Accepted |
Mar 24, 2022 | Project Manager |
Apr 18, 2022 | HPHC Historical Preservation No Effect |
Jun 03, 2022 | Biologist Report |
Jun 14, 2022 | Typist for Processing |
Jun 14, 2022 | Executive Sign Off |
Jun 14, 2022 | Sent to Photo Copy |
Jun 14, 2022 | Permit Approved |
Jun 14, 2022 | Permit Mailed |
Jul 12, 2022 | Land Evidence Date |