Action Date | Action Description |
---|---|
Sep 28, 2015 | Assent Application Received |
Sep 30, 2015 | Administrative Review for Completeness |
Sep 30, 2015 | Team Review for Completeness |
Sep 30, 2015 | Application Accepted |
Oct 06, 2015 | HPHC Historical Preservation No Effect |
Oct 14, 2015 | Additional Information Received |
Dec 01, 2015 | 30 day Public Notice Issued |
Dec 02, 2015 | Plans Received |
Dec 30, 2015 | Category A* (Docks) |
Jan 01, 2016 | Public Notice End Date |
Jan 21, 2016 | Dock Meeting -- Approval |
Jan 26, 2016 | US Army Corps of Engineers Approval Received |
Jan 28, 2016 | Biologist Report |
Feb 01, 2016 | Typist for Processing |
Feb 02, 2016 | Executive Sign Off |
Feb 02, 2016 | Sent to Photo Copy |
Feb 02, 2016 | Permit Approved |
Feb 12, 2016 | Land Evidence Date |