Action Date | Action Description |
---|---|
HPHC Historical Preservation No Effect | |
Dock Post-Construction Certification by Engineer received. | |
Feb 18, 1988 | Application Accepted |
Mar 23, 1988 | Historical Preservation Approval Granted |
Apr 21, 1988 | 30 day Public Notice Issued |
Jul 15, 1988 | Water Quality Certification |
Jul 20, 1988 | Biologist Report |
Jul 20, 1988 | Engineering Report |
Sep 07, 1988 | Permit Approved |
Jun 14, 2016 | Modification Request |
Jun 14, 2016 | Administrative Review for Completeness |
Jun 17, 2016 | Team Review for Completeness |
Jun 17, 2016 | Additional Information Received |
Jun 17, 2016 | Application Accepted |
Oct 03, 2016 | Additional Information Received |
Oct 06, 2016 | Biologist Report |
Oct 18, 2016 | Typist for Processing |
Oct 18, 2016 | Executive Sign Off |
Oct 18, 2016 | Sent to Photo Copy |
Oct 18, 2016 | Modification Approved |
Nov 17, 2016 | Modification Request |
Nov 30, 2016 | Administrative Review for Completeness |
Dec 01, 2016 | Team Review for Completeness |
Dec 01, 2016 | Application Accepted |
Dec 29, 2016 | Plans Received |
Jan 10, 2017 | 30 day Public Notice Issued |
Feb 10, 2017 | Public Notice End Date |
Mar 15, 2017 | US Army Corps of Engineers Approval Received |
Mar 20, 2017 | Dock/1.1.6 Review approval |
Mar 23, 2017 | Biologist Report |
Mar 24, 2017 | Typist for Processing |
Mar 24, 2017 | Executive Sign Off |
Mar 24, 2017 | Sent to Photo Copy |
Mar 24, 2017 | Modification Approved |
Apr 13, 2017 | Land Evidence Date |