Action Date | Action Description |
---|---|
Aug 10, 1989 | ISDS Approved |
Dec 10, 1990 | Application Accepted |
Dec 19, 1990 | Historical Preservation Approval Granted |
Apr 04, 1991 | 30 day Public Notice Issued |
Nov 08, 1991 | Water Quality Certification |
May 15, 1992 | Biologist Report |
May 26, 1992 | Meeting Held |
Jul 14, 1992 | Meeting Held |
Jul 28, 1992 | Meeting Held |
Jul 28, 1992 | Council Approval Granted |
Nov 25, 1992 | Engineering Report |
Dec 01, 1992 | Permit Approved |
Dec 17, 1992 | Land Evidence Date |