Action Date | Action Description |
---|---|
Apr 21, 2000 | Application Accepted |
May 02, 2000 | Historical Preservation Approval Granted |
May 03, 2000 | 30 day Public Notice Issued |
Jun 25, 2000 | Engineering Report |
Jun 26, 2000 | Biologist Report |
Sep 26, 2000 | Meeting Held |
Oct 05, 2000 | Permit Approved |
Oct 05, 2000 | Land Evidence Date |
Mar 08, 2001 | Council Approval Granted |
Jul 02, 2012 | Modification Request |
Jul 05, 2012 | Administrative Review for Completeness |
Jul 09, 2012 | Team Review for Completeness |
Jul 12, 2012 | 30 day Public Notice Issued |
Aug 12, 2012 | Public Notice End Date |
Aug 30, 2012 | Typist for Processing |
Aug 30, 2012 | Engineering Report |
Aug 30, 2012 | Biologist Report |
Aug 30, 2012 | Modification Approved |
Aug 30, 2012 | Pre-construction requirement by CRMC staff |
Sep 04, 2012 | Executive Sign Off |
Sep 04, 2012 | Sent to Photo Copy |
Oct 12, 2012 | US Army Corps of Engineers Approval Received |
Dec 05, 2012 | Land Evidence Date |