Action Date | Action Description |
---|---|
Dec 06, 2001 | Application Accepted |
Dec 06, 2001 | Category B assigned |
Dec 18, 2001 | Historical Preservation Approval Granted |
Feb 02, 2002 | 30 day Public Notice Issued |
Feb 06, 2002 | Engineering Report |
Mar 12, 2002 | Meeting Held |
Jul 22, 2002 | Permit Approved |
Oct 24, 2002 | Council Approval Granted |
May 02, 2003 | Modification Request |
May 15, 2003 | Modification Approved |
Oct 25, 2004 | Assent Amended |
Dec 10, 2004 | Water Quality Certification |
Feb 17, 2005 | Extension of Permit Request |
Feb 21, 2005 | Extension Approved |
Mar 03, 2005 | Assent Amended |
Mar 25, 2005 | Water Quality Certification |
Nov 21, 2005 | Modification Approved |
Mar 24, 2006 | Correspondence Received |
Mar 24, 2006 | Extension of Permit Request |
Dec 21, 2006 | Modification Request |
Jan 10, 2007 | Typist for Processing |
Jan 10, 2007 | Executive Sign Off |
Jan 10, 2007 | Sent to Photo Copy |
Jan 10, 2007 | Assent Amended |
Jan 10, 2007 | Modification Approved |
Jan 11, 2007 | Extension Approved |
Jan 11, 2007 | Administrative Review for Completeness |
Feb 27, 2007 | Assent Amended |
May 14, 2007 | Extension of Permit Request |
May 23, 2007 | Enforcement Compliance Inspection Required |
May 23, 2007 | Process Extension |
May 23, 2007 | Extension Approved |
Mar 17, 2009 | Additional Information Received |
Mar 27, 2009 | Modification Approved |
Jun 17, 2011 | Additional Information Received |
Jun 27, 2011 | Letter of Authorization |
Jun 05, 2012 | Extension Toll letter mailed |
Aug 06, 2012 | Additional Information Received |
Aug 09, 2012 | Assent Amended |
Oct 20, 2014 | Modification Request |
Oct 23, 2014 | Administrative Review for Completeness |
Oct 23, 2014 | Team Review for Completeness |
Feb 03, 2015 | Correspondence Received |
Mar 24, 2015 | Correspondence Mailed/Faxed/E-mailed |
Jan 06, 2016 | Correspondence Received |
Feb 02, 2016 | Modification Request |
Feb 11, 2016 | Engineering Report |
Feb 11, 2016 | Typist for Processing |
Feb 11, 2016 | Executive Sign Off |
Feb 11, 2016 | Sent to Photo Copy |
Feb 11, 2016 | Modification Approved |
Feb 11, 2016 | Biologist Report |
Feb 11, 2016 | Engineering Report |
Mar 11, 2016 | Land Evidence Date |
Jul 12, 2018 | Extension of Permit Request |
Jul 17, 2018 | Typist for Processing |
Jul 17, 2018 | Extension Approved |
Jan 11, 2019 | Plans Received |
Feb 05, 2019 | Modification Request |
Feb 08, 2019 | Team Review for Completeness |
Feb 08, 2019 | Application Accepted |
Mar 11, 2019 | HPHC Review Pending |
Mar 11, 2019 | HPHC Historical Preservation No Effect |
Mar 14, 2019 | Additional Information Received |
Mar 14, 2019 | Modification Approved |
Mar 14, 2019 | Engineering Report |
Apr 02, 2019 | Extension of Permit Request |
Apr 11, 2019 | Ready to Schedule Semi-Monthly Meeting |
Apr 11, 2019 | Mail Agenda Notice |
Apr 23, 2019 | Council Approval - Extension Granted |
Apr 23, 2019 | Semi-Monthly Meeting Date Scheduled |
May 21, 2019 | Typist for Processing |
May 21, 2019 | Extension Approved |