Action Date |
Action Description |
Sep 30, 2002 |
Application Accepted |
Oct 31, 2002 |
Engineering Report |
Nov 13, 2002 |
Permit Approved |
Nov 13, 2002 |
Land Evidence Date |
Apr 08, 2019 |
Correspondence Mailed/Faxed/E-mailed |
Apr 22, 2019 |
Modification Request |
Apr 24, 2019 |
Administrative Review for Completeness |
Apr 24, 2019 |
Team Review for Completeness |
Apr 24, 2019 |
Application Accepted |
Apr 25, 2019 |
Category A* (Docks) |
May 08, 2019 |
Biologist Report |
May 09, 2019 |
Modification Approved |
May 10, 2019 |
HPHC Historical Preservation No Effect |
May 10, 2019 |
HPHC Review Pending |
Jun 17, 2019 |
Assent Requirement |
Nov 30, 2020 |
Modification Request |
Dec 01, 2020 |
Administrative Review for Completeness |
Dec 03, 2020 |
Bio Team Review for Completeness |
Dec 04, 2020 |
Application Accepted |
Dec 23, 2020 |
HPHC Historical Preservation No Effect |
Dec 23, 2020 |
HPHC Review Pending |
Dec 28, 2020 |
30 day Public Notice Issued |
Jan 28, 2021 |
Public Notice End Date |
Feb 22, 2021 |
Plans Received |
Feb 26, 2021 |
Additional Information Received |
Mar 01, 2021 |
Additional Information Received |
Mar 04, 2021 |
30 day Public Notice Issued |
Mar 08, 2021 |
Additional Information Received |
Apr 01, 2021 |
Entry of Appearance Received |
Apr 04, 2021 |
Public Notice End Date |
May 18, 2021 |
Plans Received |
May 25, 2021 |
30 day Public Notice Issued |
Jun 24, 2021 |
Objections/Comments Received |
Jun 24, 2021 |
Entry of Appearance Received |
Jun 25, 2021 |
Public Notice End Date |
Jul 23, 2021 |
Additional Information Received |
Aug 03, 2021 |
Additional Information Received |
Sep 14, 2021 |
Additional Information Received |
Nov 08, 2021 |
Objections/Comments Received |
Aug 15, 2022 |
Additional Information Received |
Oct 17, 2022 |
30-Day Notification of Cancellation letter |
Nov 09, 2022 |
Plans Received |
Nov 22, 2022 |
30 day Public Notice Issued |
Nov 25, 2022 |
Additional Information Received |
Dec 09, 2022 |
Objections/Comments Received |
Dec 12, 2022 |
Objections/Comments Received |
Dec 22, 2022 |
Public Notice End Date |
Dec 30, 2022 |
Objections/Comments Received |
Jan 31, 2023 |
Additional Information Received |
Feb 06, 2023 |
Plans Received |
Feb 13, 2023 |
Additional Information Received |
Mar 16, 2023 |
Additional Information Received |
Jun 08, 2023 |
Objection withdrawal received |
Aug 01, 2023 |
Dock/1.1.6 Review approval |
Sep 13, 2023 |
Biologist Report |
Sep 19, 2023 |
Typist for Processing |
Sep 19, 2023 |
Executive Sign Off |
Sep 19, 2023 |
Sent to Photo Copy |
Sep 19, 2023 |
Modification Approved |
Sep 20, 2023 |
Permit Mailed |
Oct 23, 2023 |
Land Evidence Date |
Sep 24, 2024 |
Dock Plate re-issue |