Action Date | Action Description |
---|---|
Mar 18, 2003 | Application Accepted |
Apr 03, 2003 | Historical Preservation Approval Granted |
Oct 10, 2006 | Typist for Processing |
Oct 10, 2006 | Executive Sign Off |
Oct 10, 2006 | Sent to Photo Copy |
Oct 10, 2006 | Permit Approved |
Oct 26, 2006 | Land Evidence Date |
Jun 12, 2009 | Extension of Permit Request |
Oct 06, 2009 | Enforcement Compliance Inspection Required |
Oct 07, 2009 | Process Extension |
Oct 07, 2009 | Typist for Processing |
Oct 07, 2009 | Executive Sign Off |
Oct 07, 2009 | Sent to Photo Copy |
Oct 07, 2009 | Extension Approved |
Oct 01, 2012 | Extension Toll letter mailed |
Feb 04, 2015 | Extension Toll letter mailed |
May 24, 2017 | Extension of Permit Request |
May 25, 2017 | Extension Approved |