Action Date | Action Description |
---|---|
Apr 14, 2003 | Application Accepted |
Apr 24, 2003 | Historical Preservation Approval Granted |
Apr 05, 2004 | 30 day Public Notice Issued |
Dec 01, 2004 | Dredge Report |
Dec 01, 2004 | Biologist Report |
Dec 01, 2004 | Engineering Report |
Dec 03, 2004 | Water Quality Certification |
Jan 21, 2005 | US Army Corp of Engineers Permit Date |
Jan 31, 2005 | Semi-Monthly Meeting Date Scheduled |
Jan 31, 2005 | Mail Agenda Notice |
Jan 31, 2005 | Ready to Schedule Semi-Monthly Meeting |
Feb 08, 2005 | Semi-Monthly Meeting Held |
Feb 08, 2005 | Council Approval Granted |
Feb 16, 2005 | Permit Approved |
Feb 16, 2005 | Stipulation Package from Dredge Coordinator |
Feb 16, 2005 | Typist for Processing |
Feb 17, 2005 | Executive Sign Off |
Feb 18, 2005 | Sent to Photo Copy |
Mar 01, 2005 | Land Evidence Date |
Mar 01, 2005 | Legal Response/Decision |
Jul 27, 2007 | Extension of Permit Request |
Aug 16, 2007 | Enforcement Compliance Inspection Required |
Aug 21, 2007 | Process Extension |
Aug 21, 2007 | Typist for Processing |
Aug 21, 2007 | Executive Sign Off |
Aug 21, 2007 | Sent to Photo Copy |
Aug 21, 2007 | Extension Approved |