Action Date | Action Description |
---|---|
May 07, 2004 | Application Accepted |
May 20, 2004 | Historical Preservation Approval Granted |
May 24, 2004 | 30 day Public Notice Issued |
Aug 14, 2004 | Dock sub-committee Approved |
Aug 17, 2004 | Engineering Report |
Aug 23, 2004 | Permit Approved |
Aug 23, 2004 | Land Evidence Date |
Sep 23, 2004 | Permit Approved |
Aug 05, 2009 | Modification Request |
Aug 06, 2009 | Administrative Review for Completeness |
Aug 12, 2009 | Team Review for Completeness |
Aug 12, 2009 | Team Review for Completeness |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Sep 17, 2009 | Additional Information Requested from Applicant |
May 10, 2010 | Certified Receipt Received |
May 28, 2010 | Additional Information Received |
Jul 14, 2010 | 30 day Public Notice Issued |
Aug 14, 2010 | Public Notice End Date |
Aug 25, 2010 | Dock Meeting -- Approval |
Aug 25, 2010 | Biologist Report |
Aug 25, 2010 | Engineering Report |
Sep 08, 2010 | Typist for Processing |
Sep 08, 2010 | Executive Sign Off |
Sep 08, 2010 | Sent to Photo Copy |
Sep 08, 2010 | Modification Approved |
Sep 15, 2010 | Land Evidence Date |
Sep 29, 2010 | US Army Corp of Engineers Permit Date |