Action Date | Action Description |
---|---|
Sep 20, 2004 | Application Accepted |
Sep 20, 2004 | Category A* (Docks) |
Sep 29, 2004 | Historical Preservation Approval Granted |
Nov 19, 2004 | 30 day Public Notice Issued |
Feb 01, 2005 | Additional Information Requested from Applicant |
Feb 07, 2005 | US Army Corp of Engineers Permit Date |
Feb 09, 2005 | US Army Corps of Engineers Approval Received |
Apr 05, 2005 | Plans Received |
Apr 18, 2005 | Executive Sign Off |
Apr 18, 2005 | Biologist Report |
Apr 18, 2005 | Engineering Report |
May 03, 2005 | Ready to Schedule Semi-Monthly Meeting |
May 03, 2005 | Mail Agenda Notice |
May 10, 2005 | Semi-Monthly Meeting Held |
May 10, 2005 | Council Approval Granted |
May 10, 2005 | Semi-Monthly Meeting Date Scheduled |
Jun 07, 2005 | Stipulation Package from Biologist |
Jun 07, 2005 | Stipulation Package by Engineer |
Jun 08, 2005 | Typist for Processing |
Jun 08, 2005 | Executive Sign Off |
Jun 08, 2005 | Sent to Photo Copy |
Jun 08, 2005 | Permit Approved |
Sep 19, 2005 | Biologist Report |
Sep 19, 2005 | Executive Sign Off |
Sep 19, 2005 | Legal Response/Decision |