Action Date | Action Description |
---|---|
Enforcement Compliance Inspection Required | |
Jun 05, 2006 | Assent Application Received |
Jun 05, 2006 | Administrative Review for Completeness |
Jun 07, 2006 | Team Review for Completeness |
Jun 07, 2006 | Application Accepted |
Jun 07, 2006 | Category A* (Docks) |
Jun 13, 2006 | 30 day Public Notice Issued |
Jun 23, 2006 | HPHC Historical Preservation No Effect |
Jul 13, 2006 | Public Notice End Date |
Jul 20, 2006 | Plans Received |
Jul 28, 2006 | Dock Meeting Scheduled (Admin) |
Jul 28, 2006 | Typist for Processing |
Jul 28, 2006 | Executive Sign Off |
Jul 28, 2006 | Sent to Photo Copy |
Jul 28, 2006 | Biologist Report |
Jul 28, 2006 | Engineering Report |
Jul 28, 2006 | Permit Approved |
Aug 01, 2006 | US Army Corp of Engineers Permit Date |
Aug 02, 2006 | US Army Corps of Engineers Approval Received |
Aug 03, 2006 | Land Evidence Date |
Nov 22, 2006 | Commencement of Work Notice received |
Apr 27, 2009 | Extension of Permit Request |
Oct 13, 2009 | Enforcement Compliance Inspection Required |
Sep 18, 2014 | Process Extension |
Jul 02, 2015 | Extension of Permit Request |
Jul 02, 2015 | Management Review |
Jul 02, 2015 | Extension Denied |
Oct 30, 2015 | Correspondence Received |
Nov 20, 2015 | Correspondence Mailed/Faxed/E-mailed |
Oct 10, 2017 | Correspondence Received |
Oct 27, 2017 | Extension of Permit Request |