Action Date | Action Description |
---|---|
Sep 28, 2006 | Freshwater Wetland - Preliminary Determination |
Sep 29, 2006 | Administrative Review for Completeness |
Oct 06, 2006 | Team Review for Completeness |
Oct 06, 2006 | Application Accepted |
Oct 24, 2006 | HPHC Historical Preservation No Effect |
Nov 06, 2006 | Biologist Report |
Nov 08, 2006 | Typist for Processing |
Nov 08, 2006 | Executive Sign Off |
Nov 08, 2006 | Sent to Photo Copy |
Nov 08, 2006 | Permit Approved |
Nov 17, 2006 | Land Evidence Date |
Sep 08, 2009 | Correspondence Received |
Sep 21, 2009 | Extension of Permit Request |
Oct 01, 2009 | Enforcement Compliance Inspection Required |
Oct 07, 2009 | Process Extension |
Oct 07, 2009 | Typist for Processing |
Oct 07, 2009 | Executive Sign Off |
Oct 07, 2009 | Sent to Photo Copy |
Oct 07, 2009 | Extension Approved |