Action Date | Action Description |
---|---|
Apr 27, 2007 | Assent Application Received |
Apr 27, 2007 | Administrative Review for Completeness |
May 08, 2007 | Team Review for Completeness |
May 08, 2007 | Application Accepted |
May 08, 2007 | Biologist Report |
May 08, 2007 | Typist for Processing |
May 08, 2007 | Executive Sign Off |
May 08, 2007 | Sent to Photo Copy |
May 08, 2007 | Permit Approved |
May 11, 2007 | Land Evidence Date |
Jun 18, 2007 | Commencement of Work Notice received |
Oct 26, 2011 | Extension Toll letter mailed |
Dec 05, 2013 | Extension Toll letter mailed |
Nov 26, 2014 | Extension Toll letter mailed |
May 12, 2016 | Extension Toll letter mailed |
Nov 02, 2017 | Extension of Permit Request |
Nov 06, 2017 | Enforcement Compliance Inspection Required |
Nov 07, 2017 | Process Extension |
Nov 07, 2017 | Extension Approved |
Oct 31, 2018 | Extension of Permit Request |
Nov 28, 2018 | Enforcement Compliance Inspection Required |
Dec 03, 2018 | Process Extension |
Dec 03, 2018 | Typist for Processing |
Dec 03, 2018 | Executive Sign Off |
Dec 03, 2018 | Extension Approved |
Nov 07, 2019 | Extension of Permit Request |
Dec 04, 2019 | Extension Approved |
Nov 09, 2020 | Extension of Permit Request |
Dec 22, 2020 | Enforcement Compliance Inspection Required |
Dec 29, 2020 | Ready to Schedule Semi-Monthly Meeting |
Dec 29, 2020 | Mail Agenda Notice |
Jan 12, 2021 | Council Approval Granted |
Jan 12, 2021 | Extension Approved |
Jan 12, 2021 | Semi-Monthly Meeting Date Scheduled |