Action Date | Action Description |
---|---|
Feb 15, 2008 | Assent Application Received |
Feb 15, 2008 | Administrative Review for Completeness |
Mar 12, 2008 | Team Review for Completeness |
Mar 12, 2008 | Application Accepted |
Apr 21, 2008 | HPHC Historical Preservation No Effect |
May 21, 2008 | Biologist Report |
May 23, 2008 | Engineering Report |
May 27, 2008 | Typist for Processing |
May 27, 2008 | Executive Sign Off |
May 27, 2008 | Sent to Photo Copy |
May 27, 2008 | Permit Approved |
Jun 16, 2008 | Land Evidence Date |
Oct 26, 2011 | Extension Toll letter mailed |
Feb 04, 2015 | Extension Toll letter mailed |
Sep 29, 2016 | Extension Toll letter mailed |
Dec 05, 2016 | Modification Request |
Dec 07, 2016 | Administrative Review for Completeness |
Dec 23, 2016 | Team Review for Completeness |
Dec 23, 2016 | Team Review for Completeness |
Dec 23, 2016 | Application Accepted |
Jan 09, 2017 | HPHC Historical Preservation No Effect |
Feb 23, 2017 | Biologist Report |
Feb 23, 2017 | Engineering Report |
Feb 23, 2017 | Typist for Processing |
Feb 23, 2017 | Executive Sign Off |
Feb 23, 2017 | Sent to Photo Copy |
Feb 23, 2017 | Modification Approved |