Action Date | Action Description |
---|---|
May 13, 2008 | Assent Application Received |
May 14, 2008 | Administrative Review for Completeness |
May 14, 2008 | Team Review for Completeness |
May 14, 2008 | Team Review for Completeness |
May 14, 2008 | Application Accepted |
May 15, 2008 | Biologist Report |
May 15, 2008 | Engineering Report |
May 15, 2008 | Typist for Processing |
May 15, 2008 | Executive Sign Off |
May 15, 2008 | Sent to Photo Copy |
May 15, 2008 | Permit Approved |
May 20, 2008 | Correspondence Received |
Jun 06, 2008 | HPHC Historical Preservation No Effect |
Aug 06, 2008 | Assent Amended |
Aug 14, 2008 | Correspondence Received |
Aug 14, 2008 | Land Evidence Date |
Sep 15, 2008 | Commencement of Work Notice received |