Action Date | Action Description |
---|---|
Jul 21, 2008 | Assent Application Received |
Jul 22, 2008 | Administrative Review for Completeness |
Aug 01, 2008 | Additional Information Received |
Aug 12, 2008 | Team Review for Completeness |
Sep 16, 2008 | Typist for Processing |
Sep 16, 2008 | Biologist Report |
Sep 16, 2008 | Executive Sign Off |
Sep 16, 2008 | Sent to Photo Copy |
Sep 16, 2008 | Permit Approved |
Nov 24, 2008 | Maintenance Certification Request |
Dec 01, 2008 | Administrative Review for Completeness |
Dec 08, 2008 | Team Review for Completeness |
Dec 11, 2008 | Biologist Report |
Dec 11, 2008 | Typist for Processing |
Dec 11, 2008 | Executive Sign Off |
Dec 11, 2008 | Sent to Photo Copy |
Dec 11, 2008 | Modification Approved |
Jan 16, 2009 | Land Evidence Date |
Mar 02, 2011 | Modification Request |
Mar 02, 2011 | Administrative Review for Completeness |
May 11, 2011 | Team Review for Completeness |
May 11, 2011 | Deficient Application - Owner Notification Sent |
Jul 16, 2012 | Deficient Application Discarded/No deficiency Reponse |