Action Date | Action Description |
---|---|
Aug 08, 2008 | Assent Application Received |
Aug 14, 2008 | Team Review for Completeness |
Aug 14, 2008 | Application Accepted |
Aug 28, 2008 | 30 day Public Notice Issued |
Sep 25, 2008 | Dock/1.1.6 Review approval |
Sep 27, 2008 | Public Notice End Date |
Oct 01, 2008 | Engineering Report |
Oct 02, 2008 | Typist for Processing |
Oct 02, 2008 | Executive Sign Off |
Oct 02, 2008 | Sent to Photo Copy |
Oct 02, 2008 | Permit Approved |