Action Date | Action Description |
---|---|
Oct 07, 2008 | Assent Application Received |
Oct 07, 2008 | Administrative Review for Completeness |
Oct 14, 2008 | Team Review for Completeness |
Oct 14, 2008 | Team Review for Completeness |
Oct 14, 2008 | Application Accepted |
Oct 14, 2008 | Category A* (Docks) |
Oct 17, 2008 | HPHC Historical Preservation No Effect |
Oct 23, 2008 | 30 day Public Notice Issued |
Nov 23, 2008 | Public Notice End Date |
Jan 14, 2009 | US Army Corp of Engineers Permit Date |
Jan 16, 2009 | US Army Corps of Engineers Approval Received |
Jan 27, 2009 | Additional Information Received |
Jan 27, 2009 | Typist for Processing |
Jan 27, 2009 | Executive Sign Off |
Jan 27, 2009 | Sent to Photo Copy |
Jan 27, 2009 | Permit Approved |
Jan 27, 2009 | Biologist Report |
Jan 27, 2009 | Engineering Report |
Mar 30, 2009 | Land Evidence Date |
Jan 25, 2011 | Extension of Permit Request |
Jan 26, 2011 | Correspondence Received |
Feb 25, 2011 | Extension Toll letter mailed |
Jul 12, 2013 | Extension Toll letter mailed |