Jul 12, 2010 | Assent Application Received |
Jul 13, 2010 | Administrative Review for Completeness |
Jul 19, 2010 | Team Review for Completeness |
Jul 22, 2010 | Application Accepted |
Aug 04, 2010 | HPHC Historical Preservation No Effect |
Aug 12, 2010 | Geologist Report |
Aug 13, 2010 | Typist for Processing |
Aug 13, 2010 | Permit Approved |
Aug 16, 2010 | Executive Sign Off |
Aug 16, 2010 | Sent to Photo Copy |
Aug 27, 2010 | Land Evidence Date |
Sep 27, 2010 | Commencement of Work Notice received |