Image not found

Application 2011-08-016 Details

Back to List


Actions:

Action Date Action Description
Aug 04, 2011 Dredge Application
Aug 05, 2011 Administrative Review for Completeness
Aug 09, 2011 Team Review for Completeness
Aug 09, 2011 Application Accepted
Aug 16, 2011 HPHC Historical Preservation No Effect
Aug 22, 2011 Joint Public Notice
Sep 22, 2011 Public Notice End Date
Sep 30, 2011 Engineering Report
Oct 04, 2011 Permit Approved
Oct 04, 2011 Typist for Processing
Oct 05, 2011 Executive Sign Off
Oct 05, 2011 Sent to Photo Copy
Oct 21, 2011 US Army Corps of Engineers Approval Received
Oct 24, 2011 Assent Correction Mailed
Nov 01, 2011 Land Evidence Date
Nov 01, 2011 Land Evidence Date
Feb 13, 2012 Correspondence Mailed/Faxed/E-mailed
Feb 13, 2012 Dredge Application
Feb 16, 2012 Assent Correction Mailed
Feb 24, 2012 CAD Cell Fee Due-Final
Apr 23, 2012 Land Evidence Date

Details:

File No
2011-08-016
Town
Providence
First Name
SIMS Metal Management
Last Name
Street
Allens Avenue
Location
242 Allens Avenue
Plat/Map
47
Lot/Block
803
Decision Date
Oct 04, 2011
Dock Reg.No
Project
dredge approx.29,700cuyds at berth adjacent to pier
Description
Dredging (Improvements)
Water Area
Providence River (Harbor Area)
Easement
0
Acceptance Date
Aug 09, 2011

Back to List