Action Date | Action Description |
---|---|
Oct 25, 2011 | Assent Application Received |
Oct 26, 2011 | Administrative Review for Completeness |
Nov 01, 2011 | Team Review for Completeness |
Nov 01, 2011 | Team Review for Completeness |
Nov 01, 2011 | Category B assigned |
Nov 01, 2011 | Application Accepted |
Nov 14, 2011 | 30 day Public Notice Issued |
Nov 23, 2011 | HPHC Historical Preservation No Effect |
Dec 01, 2011 | Public Notice End Date Extension Granted |
Dec 14, 2011 | Objections/Comments Received |
Dec 14, 2011 | Public Notice End Date |
Dec 27, 2011 | Biologist Report |
Dec 27, 2011 | Engineering Report |
Jan 10, 2012 | Semi-Monthly Meeting Held |
Jan 10, 2012 | Council Approval Granted |
Jan 13, 2012 | Correspondence Received |
Jan 19, 2012 | US Army Corps of Engineers Approval Received |
Jan 20, 2012 | Plans Received |
Jan 25, 2012 | Permit Approved |
Jan 25, 2012 | Stipulation Package from Biologist |
Jan 25, 2012 | Stipulation Package by Engineer |
Jan 25, 2012 | Legal Response/Decision |
Jan 27, 2012 | Typist for Processing |
Jan 30, 2012 | Executive Sign Off |
Jan 30, 2012 | Sent to Photo Copy |
Feb 07, 2012 | Land Evidence Date |