Action Date | Action Description |
---|---|
Dec 01, 2011 | Freshwater Wetland - Request to Alter |
Dec 02, 2011 | Administrative Review for Completeness |
Dec 06, 2011 | Application Accepted |
Dec 13, 2011 | HPHC Historical Preservation No Effect |
Mar 27, 2012 | Team Review for Completeness |
Mar 27, 2012 | Application Accepted |
Mar 27, 2012 | Biologist Report |
Mar 28, 2012 | Typist for Processing |
Mar 28, 2012 | Executive Sign Off |
Mar 28, 2012 | Sent to Photo Copy |
Mar 28, 2012 | Permit Approved |
Jun 06, 2013 | Freshwater Wetland - Permit Modification Request |
Jun 06, 2013 | Administrative Review for Completeness |
Aug 07, 2013 | Team Review for Completeness |
Aug 08, 2013 | Typist for Processing |
Aug 08, 2013 | Executive Sign Off |
Aug 08, 2013 | Sent to Photo Copy |
Aug 08, 2013 | Modification Approved |
Sep 06, 2013 | Modification Request |
Sep 09, 2013 | Administrative Review for Completeness |
Nov 21, 2013 | Modification Request |
Nov 22, 2013 | Duplicate Original Assent requested/mailed |
Dec 03, 2013 | Land Evidence Date |
Mar 13, 2014 | Biologist Report |
Mar 13, 2014 | Typist for Processing |
Mar 13, 2014 | Modification Approved |
Mar 14, 2014 | Executive Sign Off |
Mar 14, 2014 | Sent to Photo Copy |
May 02, 2014 | Land Evidence Date |
Dec 17, 2014 | Plans Received |
Mar 07, 2019 | Expiration of Assent/End of Tolling Legislation |