Action Date | Action Description |
---|---|
Dec 12, 2011 | Assent Application Received |
Dec 14, 2011 | Application Accepted |
Dec 22, 2011 | Correspondence Mailed/Faxed/E-mailed |
Jan 10, 2012 | Correspondence Received |
Jan 10, 2012 | Correspondence Received |
Jan 25, 2012 | Correspondence Received |
Feb 14, 2012 | Correspondence Received |
Feb 17, 2012 | Correspondence Received |
Feb 20, 2012 | Objections/Comments Received |
Feb 20, 2012 | Objections/Comments Received |
Feb 20, 2012 | Correspondence Received |
Feb 21, 2012 | Correspondence Received |
Mar 23, 2012 | Mail Agenda Notice |
Mar 26, 2012 | Biologist Report |
Mar 26, 2012 | Biologist Report |
Mar 26, 2012 | Dredge Report |
Mar 26, 2012 | Geologist Report |
Mar 26, 2012 | Report completed |
Mar 28, 2012 | Additional Information Requested from Applicant |
Apr 04, 2012 | Correspondence Received |
Apr 04, 2012 | Correspondence Received |
Apr 04, 2012 | Correspondence Received |
Apr 04, 2012 | Correspondence Received |
Apr 05, 2012 | Correspondence Received |
Apr 10, 2012 | Semi-Monthly Meeting Date Scheduled |
Apr 10, 2012 | Continued Application by the Council |
Apr 11, 2012 | Mail Agenda Notice |
Apr 13, 2012 | Objections/Comments Received |
Apr 24, 2012 | Council Decision - Denied |
Apr 24, 2012 | Semi-Monthly Meeting Date Scheduled |