Action Date | Action Description |
---|---|
Dec 14, 2011 | Assent Application Received |
Dec 14, 2011 | Administrative Review for Completeness |
Dec 19, 2011 | Team Review for Completeness |
Dec 19, 2011 | Additional Information Received |
Dec 20, 2011 | Application Accepted |
Dec 20, 2011 | Team Review for Completeness |
Dec 20, 2011 | 30 day Public Notice Issued |
Jan 14, 2012 | HPHC Historical Preservation No Effect |
Jan 20, 2012 | Public Notice End Date |
Jan 27, 2012 | Scheduled for Section 110 Review meeting |
Jan 27, 2012 | Biologist Report |
Jan 27, 2012 | Engineering Report |
Jan 30, 2012 | Supervisor Biologist SignOff |
Jan 31, 2012 | Supervisor Engineer SignOff |
Jan 31, 2012 | Executive Signoff of Staff Reports |
Feb 01, 2012 | Scheduled for Section 110 Review meeting |
Mar 30, 2012 | Stipulation Package by Engineer |
Mar 30, 2012 | Stipulation Package from Biologist |
Apr 03, 2012 | Typist for Processing |
Apr 03, 2012 | Permit Approved |
Apr 04, 2012 | Conservation Easement Mailed. |
Apr 04, 2012 | Executive Sign Off |
Apr 04, 2012 | Sent to Photo Copy |
May 22, 2012 | Land Evidence Date |
Sep 26, 2012 | Correspondence Received |
Sep 26, 2012 | Phone Call |
Jan 11, 2013 | Conservation Easement Recording received |
Mar 19, 2013 | Note to File |
Feb 03, 2014 | Correspondence Received |
Feb 03, 2014 | Correspondence Received |
Feb 03, 2014 | Correspondence Received |