Action Date | Action Description |
---|---|
Dec 22, 2011 | Assent Application Received |
Dec 22, 2011 | Administrative Review for Completeness |
Dec 22, 2011 | Team Review for Completeness |
Dec 22, 2011 | Team Review for Completeness |
Dec 22, 2011 | Application Accepted |
Dec 29, 2011 | Engineering Report |
Dec 29, 2011 | Biologist Report |
Jan 03, 2012 | Typist for Processing |
Jan 03, 2012 | Permit Approved |
Jan 04, 2012 | HPHC Historical Preservation No Effect |
Jan 04, 2012 | Executive Sign Off |
Jan 04, 2012 | Sent to Photo Copy |
Jan 06, 2012 | Land Evidence Date |