Action Date | Action Description |
---|---|
May 21, 2012 | Assent Application Received |
May 22, 2012 | Administrative Review for Completeness |
May 22, 2012 | Team Review for Completeness |
May 22, 2012 | Team Review for Completeness |
May 22, 2012 | Application Accepted |
May 23, 2012 | Biologist Report |
May 23, 2012 | Engineering Report |
May 31, 2012 | Typist for Processing |
May 31, 2012 | Permit Approved |
Jun 01, 2012 | Executive Sign Off |
Jun 01, 2012 | Sent to Photo Copy |
Jun 29, 2012 | Land Evidence Date |