Action Date | Action Description |
---|---|
Jun 18, 2012 | Assent Application Received |
Jun 18, 2012 | Administrative Review for Completeness |
Jun 18, 2012 | Team Review for Completeness |
Jun 18, 2012 | Team Review for Completeness |
Jun 18, 2012 | Application Accepted |
Jul 11, 2012 | HPHC Historical Preservation No Effect |
Jul 25, 2012 | Additional Information Received |
Jul 25, 2012 | Biologist Report |
Jul 26, 2012 | Engineering Report |
Jul 30, 2012 | Typist for Processing |
Jul 30, 2012 | Executive Sign Off |
Jul 30, 2012 | Sent to Photo Copy |
Jul 30, 2012 | Permit Approved |
Aug 14, 2012 | Land Evidence Date |